Vienna, a federal state in eastern Austria and the country’s capital, has published a new data center strategy.
Consisting of ten principles, the Vienna Data Center Strategy establishes guidelines for the facilities’ development in the Austrian capital, with an emphasis on balancing its economic base, and digital independence, against the ecological sustainability of future projects.
DCD has approached the city of Vienna for comment.
“Digital infrastructure will determine how successful Vienna as a business location will be in international competition in the future,” said the federal state’s governor and city mayor Michael Ludwig.
“In this area, we are once again taking a distinctly Viennese approach: we are not leaving the conditions under which data centers are built in Vienna to chance. With our data center strategy, we are therefore setting clear guidelines for expansion that benefits our economy, is ecologically sustainable, uses energy and resources efficiently, and strengthens Vienna’s digital independence.”
According to the strategy, future data center projects must bring benefits to the wider federal state while using a minimum of space. They must also prioritize sustainability in their operations, ideally using efficient cooling systems and redistributing waste heat from servers into nearby district heating systems.
New projects will also be steered toward sites deemed suitable by the municipal authorities. The viability of the site’s connection to the wider electricity network also has to be guaranteed early in the planning process by the local grid operator, Wiener Netze.
To ease the application process for new data centers, the strategy additionally calls for the Vienna Business Agency to become a single point of contact between developers and municipal authorities. This will be supplemented by more proactive site selection for new projects, said the federal state, and the investigation of joint development opportunities with the neighboring regions of Lower Austria and Burgenland.
Federal state authorities cited a new development by Strabag Real Estate in collaboration with the Vienna Business Agency in the city’s Seestadt Aspern district as a test case for the new strategy. When completed, the data center – which has a planned electrical connection capacity of up to 48MW – will join 27 other facilities currently operational in the capital, according to DataCenterMap. According to figures cited by the Vienna Business Agency, demand for electrical power from data centers in the federal state will reach 250MW by 2030.