Real estate firm Merlin Properties has paused work on two data centers in the Bilbao area of Spain due to issues securing power.
The company has temporarily suspended work on its Arasur 4 and 5 buildings in Álava in the Basque Country due to difficulties related to securing a local electricity supply.
Administrative issues are affecting several of Solaria’s solar projects, compromising part of the energy supply planned for these facilities.
Solaria was one of Merlin’s energy partners in the region and was supposed to provide part of the electricity needed to power both data centers through renewable generation. However, the Basque Government’s refusal to authorize several of the solar farms planned by the company has thrown the supply schedule into question.
Merlin’s CEO, Ismael Clemente, has confirmed that the company will not proceed with these developments until it has sufficient guarantees of electricity supply. As he explained, the real estate firm is already working with Solaria to explore alternatives for shifting that energy consumption to other areas of Spain with greater self-consumption capacity.
The company already has one live 24MW building in Arasur and the second is due live before the end of the year. The third building is due live next year. The latter two facilities will both total 48MW.
More projects under threat
At the same time, the new regulatory framework proposed by the government regarding data centers has continued to cause a stir ever since it was first proposed back in late August. Both Spain DC and individual companies are expressing skepticism about it.
Merlin Properties has reportedly prepared a contingency plan in anticipation of the royal decree potentially taking effect and estimates that it would need an additional €863 million to adapt its facilities.
This figure corresponds primarily to investments in battery energy storage systems (BESS) and represents an additional 11.3 percent on top of the investments already included in its plans. Merlin expects to recoup approximately 35 percent of that additional cost.
Merlin is also reportedly considering shifting part of its development capacity to Portugal and Madrid, in addition to adding a second project in Aragón.
Merlin CEO Clemente has warned that the projected energy conditions could jeopardize the €1.6bn ($1.67bn) project’s full development. The company is working to safeguard the project’s viability and anticipate the effects of the new regulations.
The first building is designed to accommodate up to 100MW of IT capacity, although it would initially operate at 2MW due to current electricity supply limitations.
Merlin, a major real estate firm, first announced plans to move into the data center space in 2021 in partnership with Edged, the then-new data center venture from Aligned founder Jakob Carnemark. Merlin has since raised more than $1bn for further data center development.
The companies are developing data centers across Spain and Portugal in Bilbao, Arasur, Madrid-Getafe, Barcelona, and Lisbon. Meta is a rumored customer, and Nebius is a confirmed customer.
Merlin has previously backed off plans for a campus in Andalusia due to energy issues.
This piece was translated from DCD’s Spanish site and edited by a member of DCD staff.